KER AMENDMENT OF THE CAPITAL EXPENSE PLAN FOR THE NEW OILSEED PROCESSING PLANT IN WESTERN UKRAINE

Kernel Holding S.A. informs that the management expectation of the capital expense related to the construction of the oilseed processing plant in western Ukraine has increased from initial US$ 180 million to US$ 279 million.
Incremental expenditure is a result of on-going changes made to the initial plant design expanding sunflower seeds in-take and storage capacity, improving capabilities of on-site truck and railway logistics along with elevated costs of construction materials reflecting global pricing trends and labor inflation. Upon commission scheduled for spring 2022, the oilseed processing plant will have the capacity to process one million tons of sunflower seeds per year. Co-generation heat and power facility adjacent to the plant will have the electricity generation capacity of 22.5 MW to produce the renewable energy from biomass.